Support Your Freedom to Speak:
A look at New York 1977 - A Year of Chaos ! Black Outs - Heat Wave ! - Summer of Sam - Looting and Rioting
channel image
Mike Martins Channel
157 Subscribers
243 views
Published 2 years ago
The New York City blackout of 1977 was an electricity blackout that affected most of New York City on July 13–14, 1977.[1][2] The only unaffected neighborhoods in the city were in southern Queens (including neighborhoods of the Rockaways), which were part of the Long Island Lighting Company system, as well as the Pratt Institute campus in Brooklyn, and a few other large apartment and commercial complexes that operated their own historic power generators.

Unlike other blackouts that affected the region, namely the Northeast blackouts of 1965 and 2003, the 1977 blackout was confined to New York City and its immediate surrounding areas. The 1977 blackout also resulted in citywide looting and other acts of criminal activity, including arson, unlike the 1965 and 2003 blackouts.

Lightning damage
The events leading up to the blackout began on July 13 at
8:37
p.m. EDT on Wednesday, with a lightning strike at Buchanan South, a substation on the Hudson River, tripping two circuit breakers in Buchanan, New York. The Buchanan South substation converted the 345,000 volts of electricity originating from the 900 MW Indian Point nuclear generating station to lower voltage for commercial use. A loose locking nut combined with a slow-acting upgrade cycle prevented the breaker from reclosing and allowing power to flow again.

A second lightning strike caused the loss of two 345 kV transmission lines, subsequent reclose of only one of the lines, and the loss of power from the nuclear plant at Indian Point. As a result of the strikes, two other major transmission lines became overloaded. Per procedure, Consolidated Edison, the power provider for New York City and some of Westchester County, tried to bring a fast-start generating station online at
8:45
p.m. EDT; however, no one was manning the station, and the remote start failed.

At
8:55
p.m., there was another lightning strike at the Sprain Brook substation in Yonkers, which took out two additional critical transmission lines. As before, only one of the lines was automatically returned to service. This outage of lines from the substation caused the remaining lines to exceed the long-term operating limits of their capacity. After this last failure, Con Edison had to manually reduce the loading on another local generator at their East River facility, due to problems at the plant. This made an already dire situation even worse.

Power reductions
At
9:14
p.m., over 30 minutes from the initial event, New York Power Pool Operators in Guilderland called for Con Edison operators to "shed load." In response, Con Ed operators initiated first a 5% system-wide voltage reduction and then an 8% reduction. These steps had to be completed sequentially and took many minutes. These steps were done in accordance with Con Edison's use of the words "shed load" while the Power Pool operators had in mind opening feeders to immediately drop about 1500 MW of load, not reduce voltage to reduce load a few hundred MW.

At
9:19
p.m., the final major interconnection to Upstate New York at Leeds substation tripped due to thermal overload which caused the 345kV conductors to sag excessively into an unidentified object. This trip caused the 138 kV links with Long Island to overload, and a major interconnection with the New Jersey Public Service Electric and Gas Company (PSEG) began to load even higher than previously reported.

At
9:22
p.m., Long Island Lighting Company opened its 345 kV interconnection to Con Edison to reduce power that was flowing through its system and overloading 138 kV submarine cables between Long Island and Connecticut. While Long Island operators were securing permission from the Power Pool operators to open their 345 kV tie to New York City, phase shifters between New York City and New Jersey were being adjusted to correct heavy flows, and this reduced the loading on the 115 kV cables. The Long Island operators did not notice the drop in 115 kV cable loadings and went ahead with opening their 345 kV tie to New York City.
Keywords
new york citydolly partonmanhattennew york 1977

FREE email alerts of the most important BANNED videos in the world

Get FREE email alerts of the most important BANNED videos in the world that are usually blacklisted by YouTube, Facebook, Google, Twitter and Vimeo. Watch documentaries the techno-fascists don't want you to know even exist. Join the free Brighteon email newsletter. Unsubscribe at any time. 100% privacy protected.

Your privacy is protected. Subscription confirmation required.